Buy now

Notice of Commencement in Miami-Dade: How to Record

In Miami-Dade, the Clerk of the Court and Comptroller is the official recorder of all instruments, and the County Recorder's Office records notices of commencement. Miami-Dade's building department then checks for a certified copy at the job site on the first inspection. Here is what both offices publish.

1. When you need one in Miami-Dade

Miami-Dade County's building page says a Notice of Commencement is required for real property improvements greater than $5,000, and that this does not apply to repair or replacement of an existing heating or air-conditioning system under $15,000. It must be recorded within 90 days before work starts and is good for one year after the recording date (sections 713.135(1) and 713.13(2)).

2. Fill in and sign

Florida uses one statewide form (section 713.13(1)(d)). Miami-Dade's page says the notice must be signed by the owner, not your agent. The Clerk records originals only, signed and notarized, with a "Prepared by" statement. If there is a payment bond, attach a copy when you record.

3. Record it with the County Recorder

OptionWhat the Clerk says
MailOffice of County Recorder, 20 NW 1st Avenue, Suite 5.246, Miami, Florida 33128, with a self-addressed stamped envelope.
eRecording Web ServiceThe Clerk's own eRecording service accepts notices of commencement. E-recorded documents take about 1 to 3 business days before they appear in public view.
E-recording vendorsCorporation Service Company (CSC); e-Docs Solutions; eRecording Partners; Hopdox; Simplifile; Swift-E Recording.
In personSee the Clerk's Official Records page for the current counter location. Credit cards are accepted only in person (daily limit $5,000).

4. The fee

The Clerk charges $10 for the first page and $8.50 for each additional page (section 28.24(13)); a two-page notice is $18.50. Copies are $1 per page plus $2 to certify. Checks are payable to "Clerk of the Court and Comptroller".

5. The first inspection

Miami-Dade's building page asks you to make sure the notice is recorded before inspections and to keep a certified copy at the construction site. The County's Notice of Commencement handout says the first inspection checks for the posted certified copy, and a missing copy results in a disapproved inspection. State law allows a notarized filed-for-recording statement with a copy in place of the certified copy (section 713.13(1)(a)).

Miami-Dade County's permitting center is at 11805 SW 26 Street, Miami, FL 33175 (call 311). Many cities in the county, such as Miami, Miami Beach and Hialeah, run their own building departments; follow the rule of the office that issued your permit. Recording still goes to the County Recorder.

6. When the job is done

The notice lasts one year unless it states a later date. If the owner's address changes, record a corrected notice. To end it early, record a Notice of Termination (section 713.132).

Fill in your Miami-Dade notice

PermitReady FL gives you the section 713.13 form with the recording space laid out, ready for the owner to sign, notarize and e-record or mail to the County Recorder, with steps in English and Spanish. See plans from $19 or use the free NOC checker. Also read our Spanish guide to the Notice of Commencement.

Other counties: Pinellas · Collier · Broward · Palm Beach · Orange · Hillsborough

Sources

Last reviewed November 21, 2026 against the Miami-Dade Clerk and Miami-Dade County pages listed above and the 2026 Florida Statutes. Some older county documents show other addresses; use the Clerk's current page. PermitReady FL is self-help form software, not a law firm, and is not affiliated with the Clerk, Miami-Dade County or any government agency.