Do You Need a Notice of Commencement in Florida?

A Notice of Commencement tells everyone who works on or supplies your job that an improvement has started, who the owner and contractor are, and where to send notices. Two sections of Florida's Construction Lien Law decide when you need one for your permit: section 713.13 (the notice itself) and section 713.135 (what building departments must do).

The $5,000 rule for the first inspection

When you apply for a building permit, section 713.135(1)(e) requires the applicant to file a copy of the Notice of Commencement with the permitting office before the first inspection if the direct contract is greater than $5,000. Any one of these counts as the copy:

  • a certified copy of the recorded notice;
  • a notarized statement that the notice has been filed for recording, together with a copy of the notice; or
  • the clerk's official records identifying information, such as the instrument number or the book and page.

If the copy is not filed, the building department or private inspection provider may not perform or approve later inspections until it is (section 713.135(1)(e)1).

The heating and air-conditioning exception

Section 713.135(1) ends with this sentence: "This subsection does not apply to a direct contract to repair or replace an existing heating or air-conditioning system in an amount less than $15,000." A like-for-like A/C changeout under $15,000 is therefore outside these permit rules.

Recording is not a condition for getting the permit

The building department may not require a recorded notice as a condition of applying for, processing or issuing a permit (section 713.135(1)(f)), and recording is not required before the permit is issued. The deadline is the first inspection.

What the notice itself requires

  • It is recorded in the county where the property is and posted at the job site before the first inspection. The posted copy is either a certified copy or the notarized filed-for-recording statement with a copy (section 713.13(1)(a)).
  • The owner signs it (section 713.13(1)(g)).
  • Work must actually start within 90 days after recording, or the notice is void and of no further effect (section 713.13(2)).
  • It expires 1 year after recording unless it states a different date. Payments made after expiration are improper payments under section 713.13.

Quick check

Your jobCopy filed before first inspection?
Direct contract over $5,000 (roof, pool, addition, windows, solar)Yes
Direct contract of $5,000 or lessNot under s. 713.135(1)(e); ask your building department
Repair or replace an existing heating or A/C system, under $15,000No, outside s. 713.135(1)

Our free checker applies these rules to your price and job type and shows the 90-day and 1-year dates from your recording date.

Sources

Last reviewed November 21, 2026 against the 2026 Florida Statutes. PermitReady FL is self-help form software and does not give legal advice; we are not affiliated with any clerk or government agency.

PermitReady FL
Florida Notices of Commencement, filled in on the statutory form and ready for the clerk. See pricing

Also from our guides